Stormwater Management Plan

Permit Registration Requirements

The following summarizes critical dates and submittal requirements in the new permit:

The permit is effective from July 1, 2017 to June 30, 2022.

On April 1, 2017, the SMP, registration form, and electronic copy are due to CT DEEP.

The SMP will be posted for public review and comment by April 1, 2017. Full development and implementation of the SMP is required within five years, specifically June by 30, 2022.

Annual reports are due to CT DEEP on April 1st of each year. On January 31st, a draft copy of each Annual report submission shall be made available for public review and comment.

After review and finalization, the report will be submitted to CT DEEP and made available to the public.

( See entire Stormwater Management Plan HERE. )